2017 Elgin Capital Improvements

Investing in Elgin: Your tax dollars at work

You’ll notice signs throughout the city identifying projects that are part of the “Investing in Elgin.” When you see those signs, know that it’s your tax dollars that made each project possible.

Here is everything you need to know about 2017 capital improvement projects:

Citywide project map

map_city17-01

Frequently Asked Questions

Capital FAQs

List of Projects:


 

Bluff City Boulevard Combined Sewer Separation

bluff-city-map

Anticipated Start Date:  February 2, 2016; Anticipated End Date: June, 2017

Status: Completed

5status-01

Funding Source: Sales Tax, Utility, 2013 General Obligation Bond

Engineering Firm: HR Green

Contractor: Benchmark Construction

Back to project list


 

Lord Street Sanitary Sewer

lord-st-01

Anticipated Start Date: February 13, 2017; Anticipated End Date: June 30, 2017

Status: Completed

5status-01

Funding Source: Capital Improvement Fund (funded through sales tax)

Engineering Firm:  Burns & McDonnell

Contractor: Martam Construction

Back to project list


 

Moseley and Orchard Area Rehabilitation

moseleyorchard-01

Anticipated Start Date: February 27, 2017; Anticipated End Date: September 30, 2017

Status: In progress

4status-01

Funding Source: Utility Fund, 2016 Bond Funds, and Riverboat Funds

Engineering Firm: Burns & McDonnell

Contractor: Trine Construction; Orange Crush

Back to project list


 

Northeast Area Resurfacing 

Northeast Area-01

Anticipated Start Date:  June 2017; Anticipated End Date: October 2017

Status: In progress

3status-01

Funding Source: Riverboat Funds

Engineering Firm: WBK Engineering

Contractor: Orange Crush

View enlarged area maps:

Back to project list


 

Northwest Area Resurfacing

NW_Area_Projects_v2-01

Anticipated Start Date: June 2017; Anticipated End Date: October 2017

Status: In Progress

3status-01

Funding Source: Riverboat Funds

Engineering Firm: Trotter and Associates, Inc.

Contractor: Arrow Road Construction

View enlarged area maps:

Back to project list


 

Southwest Area Resurfacing

Southwest Area1-01

Anticipated Start Date:  June 2017; Anticipated End Date: October 2017

Status: In Progress

3status-01

Funding Source: Riverboat Funds

Engineering Firm: Crawford Murphy and Tilly, Inc.

Contractor: Plote Construction

View enlarged area maps:

Back to project list


 

West Pressure Zone Connectivity – Phase 2

wpz-01

Anticipated Start Date: May 2017 ; Anticipated End Date: November 2017

Status: In Progress

3status-01

Funding Source: Utility Fund

Engineering Firm: Burns & McDonnell

Contractor: Trine Construction

View project documents (maps, door hangers, letters to residents, etc.)

Back to project list


 

Additional Projects

2017 Bridge/Structure Maintenance/Rehabilitation Projects

  • Bluff City Boulevard (over Poplar Creek)
  • Chicago Street Bridge (over Fox River)
  • Eagle Road Bridge (over Tyler Creek)
  • Highland Avenue Bridge (over Fox River)
  • Highland Avenue Bridge (over Pingree Creek)
  • National Street Bridge (over Fox River)
  • Royal Boulevard Bridge (over Tyler Creek)
  • Shales Parkway Bridge (over Poplar Creek)

2018 Chicago Street Reconstruction

Screen Shot 2016-03-14 at 11.53.46 AM

View project documents (maps, door hangers, letters to residents, etc.)